I just got off the phone with a solar installer and they had 2 products, one which cost nearly 60-100k to install and could be done right away because of a deal with my local gov and electric utility. Also the net metering rate and credits are getting reduced by the same utility which is actually making a return on investment harder.
OR
Another solar product costs 40k but it may take years to get approval which is not guaranteed because so far every attempt for approval from the local gov and electric utility have been in limbo or flat out denied.
I just got off the phone with a solar installer and they had 2 products, one which cost nearly 60-100k to install and could be done right away because of a deal with my local gov and electric utility. Also the net metering rate and credits are getting reduced by the same utility which is actually making a return on investment harder.
OR
Another solar product costs 40k but it may take years to get approval which is not guaranteed because so far every attempt for approval from the local gov and electric utility have been in limbo or flat out denied.
🤔
In many areas, they flat out don’t allow the second one at all.